On the last weekend of September, crews paved the south side of Mineral Avenue. The new asphalt runs from the Platte River Parkway intersection west to the bridge over the South Platte River. They also paved a new lane on the west side of Santa Fe Drive, just south of Mineral. For the next two weeks, the city's schedule called for street-light foundations and equipment for the permanent traffic signals. Most of what changes along Mineral between now and 2028 is roads, signals and trail links. Costco opens in the middle of that work. SCHEELS, the biggest destination, opens after all of it, in 2029.
What Driving Mineral Looks Like Right Now
These restrictions come from the city's Oct. 1 project update for the Santa Fe and Mineral Improvements. The city posts a new update every two weeks, so check the page before you plan around any of this.
- Mineral Avenue is down to one lane in each direction from just west of Santa Fe Drive to west of Platte River Parkway, and the signals in that stretch have been removed.
- Eastbound drivers can't turn left to or from Platte River Parkway. Signs send that traffic around through Aspen Grove and Santa Fe Drive.
- The westbound right-turn lane at Platte River Parkway is closed, so right turns happen from the through lane. No U-turns are allowed in the work zone.
- The right shoulder of southbound Santa Fe is closed around the clock for half a mile north and south of Mineral.
- People on foot or bike are routed to the crosswalk just north of the intersection, at the entrances to the 7-Eleven and the Park-n-Ride. The city says this detour is fully ADA-compliant, with ramps on both sides.
The city also warns about heavy morning and afternoon traffic, active school zones and school-bus stops inside the work area. According to the project page, this work started in late 2025 and is expected to wrap up in 2027. When it's done, the intersection gets new signals, changed lanes, safer crossings and new walking and biking connections.
The Part That Already Got Better
East of Broadway, some of the change is already finished. The city completed Phase 1 of Mineral Mobility East in spring 2026. It added buffered bike lanes, a paved all-season trail along Mineral Avenue and crossings at the High Line Canal.
So the first finished piece of the corridor's makeover is for walking and biking. That order continues. Phase 2 is in design through spring 2027, with construction planned for 2027. It covers the Mineral and Jackass Hill/Long intersection and a wider trail running west toward the RTD station. On the other side of the river, the city's Mineral Station West plan also schedules construction for 2027. It adds bike and pedestrian routes linking the RTD station, Carson Nature Center and the Mary Carter Greenway.
Put those projects together and 2027 is the year the trail network along Mineral starts to connect from the High Line Canal side to the river side.
The Order Things Arrive
Here's the sequence by target date. Some dates are firmer than others.
- Spring 2026, done: Mineral Mobility East Phase 1. The bike lanes, the all-season trail and the High Line Canal crossings.
- Spring 2027, target: Costco at Mineral Place. The Hogback Post development tracker says the city expects it to open in spring 2027.
- 2027, planned: The Santa Fe and Mineral roadwork wraps up, Mineral Mobility East Phase 2 gets built, and Mineral Station West goes to construction.
- 2028, planned: Rebuilding the Broadway/Mineral and Broadway/Littleton Boulevard intersections. In its June 2026 update, the city said the project was still in concept development, with final design set for spring 2027.
- 2029, expected: The SCHEELS store at Mineral Place.
- No date yet: 1st Street Farms at Santa Fe and Mineral, and an In-N-Out proposed at Mineral and Southpark Terrace.
One detail about the Broadway intersections matters for drivers. The city's concept work projects upgraded crossings, ramps and signals there, but only minor traffic improvements compared with doing nothing. That 2028 project is mostly about safety and access, not about moving more cars through.
Costco Comes First Among the Big Names
Mineral Place sits on the former 63-acre Lumen Technologies campus at 700 W. Mineral Ave., near South Broadway. 9News reports that its anchor will be a 159,000-square-foot Costco, the 17th Costco warehouse in Colorado. In the same report, Brian Garner, Littleton's economic development manager, called it "the biggest project that Littleton has seen in probably decades."
The city announced groundbreaking on the Costco in its July 2026 business newsletter. It hadn't set an opening date at that point. The spring 2027 target came later. Earlier forecasts had pointed to 2026.
Galloway, a firm that worked on the project, describes the full site as the Costco with a 32-pump gas station, nine small retail stores, possible restaurants and a 370-unit apartment community. None of the nine smaller shops have been named publicly. The apartments, called The Sullivan, are being developed by Embrey and are now leasing. No move-in date has been announced.
SCHEELS Is the Last Arrival, and the Largest
Mineral Place's second anchor is two years behind the first. City council approved the economic incentive package for a SCHEELS destination store by a 6–1 vote on Sept. 15, as the Denver Post reported the next day. The city's September business newsletter describes a store of about 300,000 square feet. It will have a 60-foot hubless Ferris wheel, Rollerball bowling lanes and a 16,000-gallon saltwater aquarium. The city expects it to open in 2029 and bring more than 500 retail jobs.
That puts the Ferris wheel about three years after this fall's paving. In between come the Costco, the trail links and the Broadway intersection work, in that order.
The Biggest Unknown Sits at Santa Fe and Mineral
The empty lot at the corner of Santa Fe Drive and Mineral Avenue is the one piece without a construction date. Last June, Denver7 reported that Peyton Manning is partnering with Denver-based Gastamo Group on 1st Street Farms. It's named after the street he grew up on, and the station said construction was expected to start this fall. The city's June 10 release is more cautious. It says council moved ahead with a public-private partnership, the project is heading into final design, and construction timing is "to be announced."
The plan includes a 15,000-square-foot restaurant, a 13,000-square-foot event venue and a public turf field. It also adds trails connecting to South Platte Park and the Mary Carter Greenway. Denver7 put the restaurant at 14,000 square feet and added that the field could host markets, festivals and nonprofit events. No separate restaurant brand has been named. A council packet lists Gastamo Group as the developer and the owner/operator. Like the city's road projects, this one is built around green space and trail connections.
East along Mineral, In-N-Out has filed plans for a 3,887-square-foot restaurant at Mineral and Southpark Terrace with a 30-car drive-thru queue. The site plan is still under city review, according to the Hogback Post tracker, and it's a separate site from Mineral Place.
For now, the most useful link for anyone who drives Mineral Avenue is the city's biweekly update page. Through at least 2027, it shows which turns are open between Santa Fe and Platte River Parkway.
If you're watching the Mineral corridor take shape and wondering how a 2027 Costco or a 2029 SCHEELS might fit your own plans, Maria is happy to go through the timeline with you. Gallucci Homes offers clear, patient conversations in English or ASL, whenever you're ready. Schedule an ASL-friendly consultation.